What machine loads roof tile onto a roof?

MMJ loads roof tile with a telehandler that lifts it from the truck to the roof deck. All six published MMJ loading jobs used one. Here is how the job runs.

Published · Updated · By MMJ Trucking Solutions LLC, owner Martin Mora, Florida document L22000394909, (772) 215-8374

MMJ telehandler lifting a pallet of concrete roof tile to a Florida roof

The short answer

On MMJ jobs the machine is a telehandler: a lift with a telescoping boom that raises tile from the truck or ground staging to the roof deck, where the crew spreads it. All six projects MMJ has published used one. Crane-assisted handling is reviewed when a property needs it, and sections the boom cannot reach are hand-carried.

Which machines can put roof tile on a roof?

Three methods get tile from the ground to the deck on a Florida job. A telehandler does the lifting on every rooftop loading MMJ has published, and the other two cover what the boom cannot reach.

Ways to load roof tile onto a roof, and when MMJ uses each
MethodHow the tile goes upWhen MMJ uses it
TelehandlerA telescoping boom lifts tile from the truck or ground staging to the roof edge, where the crew takes it and spreads itEvery published MMJ loading job: 6 of 6
CraneA crane lifts loads where the boom cannot reach or the building is too tallReviewed when crane-assisted handling is part of the plan, with availability, responsibilities and timing agreed first
Hand-carryWorkers carry tile up ladders or across roof sections by handSections the machine cannot reach, such as a disconnected rear roof in West Palm Beach

Truck-mounted conveyors and boom trucks are also used in the trade. MMJ's published jobs all used a telehandler. Searches for a roof tile loading machine company also return factory equipment makers that load tile into kilns at the plant; this page covers the jobsite side, from the delivery truck to the roof.

How does rooftop tile loading work, step by step?

  1. Review the site: the entrance or gate, driveway edges, swales and culverts, overhead lines and trees, the setup ground, and the roof-ready confirmation.
  2. Protect the approach: plywood goes down along the equipment path over pavers or a finished driveway.
  3. Stage the pallets at the street or driveway for the ground-to-roof handoff.
  4. Lift: the telehandler raises each load to the prepared roof. On a steep roof, lift timing is matched to the crew receiving it.
  5. Spread the load: field, trim and ridge pieces are split into bundles and working rows across the roof planes, around valleys, vents and ridges.
  6. Hand off: the tile is staged in the contractor's placement zones and the installation crew takes over.
Telehandler and ground crew coordinating a Saxony 900 rooftop tile loading in Jupiter
Pompano Beach to Jupiter, August 2026: the telehandler and ground crew hand Saxony 900 tile from staging to the roof.

What did the telehandler do on MMJ's published jobs?

Each job below combined plant pickup, jobsite delivery and rooftop loading, and each lists a telehandler as the loading equipment.

Telehandler loading on MMJ's six published projects, August to September 2026
RouteTileWhat the loading involved
Lake Wales to Boca RatonBarcelona 900Field and trim bundles placed across several roof planes and around roof features
Okeechobee to West Palm BeachVilla 900Main roof loaded by telehandler; the disconnected rear section was hand-carried
Okeechobee to JupiterSaxony 900 Split SlatePallets lifted to the roof, then split into bundles across the planes
Pompano Beach to JupiterSaxony 900, Slate Black AntiqueField, trim and ridge pieces staged around valleys and vents
Okeechobee to North Palm BeachMadera 900Steep, multi-plane roof; lift timing coordinated with the crew receiving each load
Okeechobee to Delray BeachEstateBundles staged in working rows across multiple roof planes

What does the roof need before tile is loaded?

The FRSA-TRI Florida High Wind tile manual (7th edition, effective 31 December 2023) sets three handling rules that shape every loading plan: distribute stacks of tile uniformly, not in concentrated loads; install temporary battens to help roof loading when conditions warrant; and protect the underlayment during loading and stacking. It also tells the job to make other trades aware while materials are being loaded.

Before MMJ dispatches the telehandler, the request should confirm:

  • The roof is ready to receive tile, and the date and time it will be.
  • Roof height, layout and the zones where the crew wants tile placed.
  • Tile product, quantity and pallet information.
  • A stable setup area and a clear path for the equipment.
  • Overhead, landscaping, traffic or timing restrictions.
  • The on-site contact who directs placement.

How much weight does each square put on the roof?

The five Westlake profiles in MMJ's projects install at 8.79 to 10.3 lb per square foot in the July 2026 QAI listing, so every square the telehandler lifts is roughly 880 to 1,030 lb of tile. The weight per square table breaks that down by profile.

Can MMJ load tile that another company delivered?

Yes. Loading-only requests are reviewed when the incoming delivery time, material position and quantity, equipment access, roof readiness and placement instructions are coordinated. MMJ can also pick up and deliver the tile so one company runs the job from the plant to the roof.

More questions crews ask

Is roof loading the same as roof installation?

No. MMJ raises and places the tile on the roof under the confirmed loading plan. The roofing contractor prepares the roof and installs the tile.

Will the telehandler damage a paver driveway?

MMJ lays plywood along the approved equipment path to help protect paver surfaces when the site calls for it, and five of the six published jobs record it. Gate authorization, permitted work hours and the protection plan are confirmed before the job is scheduled.

Who spreads the tile once it is on the roof?

Placement into the contractor-directed zones is part of MMJ's loading scope. On the published jobs the tile was separated into bundles and working rows across the roof planes and around valleys, vents and ridges, ready for the installation crew.

Can every jobsite be roof loaded?

No. MMJ reviews access, authorized staging, stable setup ground, overhead clearance, roof readiness, tile quantity and the contractor-directed placement plan before confirming rooftop loading.

Does MMJ work on jobs that need a crane?

MMJ reviews projects where crane-assisted handling is part of the proposed loading plan. Crane availability, responsibilities, access, timing and the approved scope are coordinated before the job is confirmed.

Sources

  1. MMJ project case studies. Equipment, site protection and rooftop placement on the six jobs published 28 August to 24 September 2026
  2. FRSA-TRI Florida High Wind Concrete and Clay Tile Installation Manual, 7th Edition. Product delivery, storage and handling; job conditions; tile installation (effective 31 December 2023; copy hosted by Eagle Roofing Products)
  3. QAI Listing B1044-2, Edition 10: Westlake Royal Roofing concrete roof tiles. Installed weight per square foot for the profiles in the project table (last revised 17 July 2026)
  4. MMJ roof tile delivery and loading FAQ. Loading scope, loading-only requests and site review (updated 28 August 2026)

Send the roof, access and placement details for a loading review.